Workers from CREC4 Eighth Engineering Co Ltd lay tracks on the Chongzuo-Pingxiang High-Speed Railway, on March 20. [Photo by WU HUAIQIU/for chinadaily.com.cn]
Lu noted that CREC4 builders only spent 144 days in completing all the track-laying work, ensuring that the average track-laying was not less than 3 kilometers per day, safeguarding the full completion on time, in quality and quantity.
The Guangxi Communications Investment Group Corp Ltd, which invested in the Chongzuo-Pingxiang section, stressed that the section boasts 165.75 kilometers of tracks laid, including 159.51 kilometers of tracks on the main line, and 6.24 kilometers of tracks within the railway stations.